How long does it take to build a brochure website?
Realistic timelines for a brochure website, step by step, and what makes a project take longer.
A bespoke brochure website usually takes 4 to 8 weeks. The schedule depends mostly on when content is available and how quickly feedback comes back.
The steps
- Scoping (3–5 days): goals, site structure, key pages, keywords.
- Wireframes (3–5 days): the structure of each page, without design.
- UI design (1–2 weeks): desktop + mobile mock-ups, component system.
- Build (1–2 weeks): development, responsive, animation, forms.
- QA & SEO (3–5 days): testing, performance, tags, redirects, go-live.
What makes a project take longer
Content that trickles in, repeated back-and-forth on the same point, pages added along the way, and no single decision-maker on the client side. Having content ready at the scoping stage can save two weeks.